This may come as a surprise; it turns out that it is shockingly hard work to build a 130′ long, 3′ high dry stack rock wall. Digging the trench for the footer alone was a massive task; it had to be around 2.5′ wide and 2′ deep and we dug it all by hand. Then 6″ of 3/4 clean gravel was added to the bottom (I used the tractor for most of this!) for drainage. We still haven’t finished setting the first course of rock. We have about 40 tons of one-man granite rocks piled in the front yard waiting to go into place although my attention has been taken lately with some interior remodeling and leak-fixing so this project has been sitting idle. Here are a few pictures of the beginnings: